…..Promised To Deliver Iseyin-Fapote-Ogbomoso Road By January
The contractor handling the Moniya-Iseyin road has begun repair works on the flooded section of the road on Monday, as instructed by the State government after the heavy downpour that led to the rising of rivers along the route.
The step was as a result of complaints from motorists plying the road, whose movements were restricted by the flood that crossed the road, which prompted the officials of the Ministry of Public Works and Transport to embark on an immediate inspection tour to the area to assess the level of damage on the affected area.
The road which was commissioned by May 2021 has been a relief to the people of Oke-Ogun and its environs as it has afforded them the opportunity to travel within less period from Ibadan to Iseyin, as different from the situation before the reconstruction.
While addressing newsmen during the inspection at chinage 47.750km of the road, the Commissioner for Public Works and Transport, Professor Dahud Kehinde Sangodoyin made it known that the cause of the damages was a result of the continuous heavy rain due to climate change and that It was not particular to only Oyo State, but all over the world.
The Commissioner explained that “we were informed that during the heavy downpour on Thursday and Friday, there were some issues as the water overflew and caused some damages by the side road, we are here to examine and assess what happened and what can be done.
“The first thing discovered is the overflow because the culverts there have been sealed up by mud, then the chainage that should be able to address the free flow of water has a problem on the other side of the road, it is not new because there is climate change all over the world, so we should prepare for it, not only in Oyo State but Nigeria as a whole.
“Work will start on it today, on the right-hand side, the channelization and on the left-hand side, retaining the walls and shifting of the culvert, in the long term, during the dry season, if we find out from weather forecast that we will have a heavy rainfall like this next year we will have to change the size of the culvert.
“The Consultant and the Contractor are with me to assess it together and we found out that it is not a serious issue but climate change that is affecting everybody all over the world, including vegetation and other things.
“I have instructed the contractor to mobilize their machine immediately so that the work can start on the channelization and to retain the wall and I can assure you that the work will start before we finish the inspection, I am assuring our people that our road is intact as it was when commissioned last year, the only damage there is on the shoulder and from today, work will start on it so that it will not hit on the road.”
The team also extended the inspection to the ongoing construction of Iseyin-Ogbomoso-Fapote road to see the progress of the project, where the Commissioner told reporters that the project would be completed by January 2023.
“They have completed the bridge around the chainage 16.0km and we are at chainage 6.0km at the culvert which is 3 by 3, as it is now, the earthwork is almost completed up to chainage 16km, the line drain is almost completed also, they have started to put the stone base from the spur which is 2km and I have advised them to put in more effort so that the contract can be completed in January 2023, as you can see, they have completed about 20% of the job at chainage 6.0km and 32.2% of job at Ogbomoso-Fapote as of last week Monday.”
Professor Sangodoyin said that the slow pace of work is due to the persistent rainfall and that the work would be faster during the dry season with proper supervision because the Government has done its part.
Buttressing the words of the Commissioner, the Consultant to the Governor on Moniya-Iseyin-Ogbomoso road construction, Engr. Wale Lagunju explained that the team has assessed the whole situation and discovered that the pavement at the flooded section of the Moniya-Iseyin road was still intact but there was need for remedial works and the Contractor has been instructed to start work immediately to make sure that the pavement does not fail so that the traffic flow would not be affected.
The Project Manager of the Construction Company, KOPEK Construction Limited, Engr Aymanza Zakhour revealed that despite what has happened, the road is still intact because the work was done with standard specification, adding that he has instructed his men to report to the construction site with machines to start the repair immediately and assured the citizenry that the work will finish in no time.
Your email address will not be published.
document.getElementById( “ak_js_1” ).setAttribute( “value”, ( new Date() ).getTime() );
OYSROMA Tests Machine To Fill Potholes Under 3 Minutes. The Oyo State Road Maintenance Agency (OYSROMA) has experi… https://t.co/p5J9UlcYKX
KOPEK To Begin Rehabilitation At Defective Part of Moniya-Iseyin Road In Accordance To Maintenance Agreement In Roa… https://t.co/wcrYJKx8lF
Oyo NNPP Officially Unveils Female Deputy Governorship Candidate For 2023 Elections. The Oyo State chapter of the… https://t.co/StDOk84iOE
2023: IGP Begins 3-Day Security Summit in Ibadan. The Inspector General of Police, Usman Baba Alkali has announced… https://t.co/OiVBZYAbM8
[…] Source link […]…
We sincerely call on the federal govt, the police, the DSS a…
[email protected]
May the Peace reign for ever in Jesus name Amen. Relevant au…
Pastor Ghandi lied about the process that “produced him “, i…